A Work Inspection Request (WIR) is the formal request a contractor sends to the consultant to inspect completed work before it is covered or the next stage starts: reinforcement before a pour, services before a ceiling closes, waterproofing before backfill. Some projects call it an inspection request or a request for acceptance of works. The name varies; the purpose is the same: proof that the work was inspected and accepted before it disappeared from view.
The value of a WIR shows months later: at a payment certificate, when a crack appears, or at handover. Then the question "Was this work inspected? Who accepted it? Against which drawing?" becomes contractual, and only a complete record answers it.
When do you submit a work inspection request?
The approved Inspection and Test Plan (ITP) sets the inspection points for each activity and their type. The most important is the hold point: the contractor cannot pass it until the consultant inspects and accepts. Next is the witness point: the consultant is notified to attend, and work may continue if they do not, as the plan states. Then the review point: the consultant reviews records without attending.
Submit a WIR at each hold or witness point, within the notice period the specification or quality plan sets. Do not submit it before the contractor's own quality team has inspected the work and confirmed it is ready. A request rejected because the work was incomplete wastes the consultant's time and delays the next stage.
What should a work inspection request include?
The project's approved form governs the final fields, but an inspectable request usually needs:
- A unique number, issue date, and discipline (civil, architectural, mechanical, electrical).
- An exact location: building, level, and zone or grid line, not just "second floor".
- The activity and the quantity to inspect with its unit, such as cubic metres or square metres.
- The ITP inspection point number and its acceptance criteria.
- The approved shop drawing and its revision, plus the related specification or method statement.
- The material approval or material inspection request (MIR) for the materials used.
- The contractor's internal inspection result, photos, and test results or survey reports where needed.
The WIR workflow from preparation to closure
- The contractor completes the work and its quality team inspects it internally against the ITP acceptance criteria.
- The site engineer prepares the request and attaches references; the quality or document control lead reviews, numbers, and logs it.
- The request goes to the consultant within the notice period the project sets.
- The consultant inspects the work on site against the approved drawing and acceptance criteria and records comments.
- A written response is issued with one of the project's codes and linked to the request and its attachments.
- On acceptance, work moves to the next stage. On rejection, the work is corrected and resubmitted as a new revision linked to the original request.
| Code | Meaning | What happens next |
|---|---|---|
| A | Accepted | Work continues; the request is kept as evidence of inspection and acceptance. |
| B | Accepted with comments | Work continues; comments are addressed and tracked to closure. |
| C | Revise and resubmit | Work does not continue; it is corrected and resubmitted as a new revision. |
| D | Rejected | Work does not continue; a nonconformance report (NCR) may be raised depending on the defect. |
The project defines what each code means, not this table. Some projects use only three codes; some allow part of the requested quantity to be accepted. What matters is that the meaning is written down before the first request and applied the same way to every request.
How a WIR differs from similar records
| Record | What it asks for | When | Usually started by |
|---|---|---|---|
| WIR — work inspection request | Inspection and acceptance of completed work | At a hold or witness point, before covering | Contractor |
| MIR — material inspection request | Inspection of delivered materials against the approval | On delivery, before use | Contractor |
| NCR — nonconformance report | Recording a defect and requiring its correction | When nonconforming work or material is found | Usually the consultant |
| RFI — request for information | Clarification of missing or conflicting information | Usually before execution | Contractor |
An MIR asks: does the material conform? A WIR asks: was the work built with it correctly? A good WIR therefore references the MIR for its materials. If the inspection finds a defect that resubmission will not fix, the right record is a nonconformance report linked to the request, not a note in the margin of the response.
How do you manage the inspection request log?
For each request the log should show the number, discipline, location, activity, ITP point, issue date, references, response due date, code, accepted quantity, and linked requests and reports. Track three indicators: overdue open requests, first-time acceptance rate, and rejection reasons by discipline and subcontractor.
The first-time acceptance rate is the most honest indicator of workmanship; a drop in one discipline shows a problem before it becomes NCRs. Repeated rejection reasons tell you what to add to the internal inspection.
Common inspection request mistakes
- Submitting before the work is complete or before the internal inspection, then being rejected for obvious reasons.
- Inspecting against an old drawing because the revision was not stated in the request.
- Covering or pouring after a verbal approval, without a recorded written response.
- Assuming acceptance because the consultant did not attend, without a contract clause that allows it.
- Resubmitting under a new, unlinked number, which breaks the history of the work.
- Keeping requests in scattered files and email, so they cannot be tied to a payment certificate when needed.
What do you need from inspection management software?
- Each request linked to the location, work item, ITP point, and approved drawing revision.
- No issue of a request at a hold point whose plan is not approved.
- Project-defined response codes, with partial acceptance of quantity.
- A response clock with alerts and escalation when overdue.
- Resubmission as a new revision linked to the original request, not a separate number.
- Accepted quantity connected to the progress and payment record.
- An audit trail that cannot be edited: who issued, who responded, when, and with what authority.
- An Arabic interface in your team's terms, not a literal translation.
How Mutamad manages work inspection requests
In Mutamad (منصة معتمد), a WIR is raised from the project's Quality Center and linked to the location, work item, and quantity to inspect, to the approved ITP point, and to the revision of the shop drawing, specification, or method statement. A hold point whose plan is not approved blocks the issue.
- The request goes through the contractor's internal review, then is formally issued after the user re-authenticates. The response works the same way.
- Response codes are defined by the project, and part of a quantity can be accepted. Codes C and D credit no accepted quantity.
- The response clock counts working days, and overdue requests are flagged and escalated with notifications.
- Accepted quantity becomes evidence in the progress and payment record once the project approves its credit rule.
- The status history is append-only: it cannot be edited or deleted.
Mutamad is before its commercial launch, and we are selecting three founding projects. The system never accepts a request or signs on anyone’s behalf; acceptance is the decision of the authorized reviewer on the project.
Frequently asked questions
What is the difference between a WIR and an MIR?
An MIR asks for inspection of materials delivered to site to confirm they match the approved material before use. A WIR asks for inspection of work built with those materials before it is covered or the next stage starts. A WIR therefore usually references the MIR for its materials.
Is a request for acceptance of works the same as a WIR?
On most Saudi projects, yes. The Arabic names vary between طلب فحص الأعمال, طلب معاينة الأعمال, and طلب استلام أعمال, but the purpose is the same: formal inspection and acceptance of completed work. The project's quality procedure is the reference.
What if the consultant does not attend the inspection?
The contract and quality plan decide. At a witness point, work may continue if the plan says so. At a hold point, work is not covered just because the time passed, unless the contract explicitly allows it. Record the notice and the non-attendance in writing on the request itself.
Is an accepted WIR enough for a payment certificate?
An accepted WIR is evidence that the work was inspected and accepted, and many projects require it before a quantity enters a payment certificate. Payment still follows the contract's measurement and certification procedure and may need other records.
The inspection request is one link in a single chain that starts with the technical submittal and passes through the material inspection request. Read the construction document management guide, or apply with your project to review your project’s inspection log.