Progress Payment Software for Construction: From Measurement to Payment Certificate and Receipt

A practical guide to construction progress payment claims: their types, what an interim claim contains, a worked example with retention, advance recovery, and VAT, the certification path from contractor to consultant and owner, and what to require from progress payment software.

Back to the blog

A progress payment claim (also called a payment application or progress claim; مستخلص in Arabic) is the periodic claim a contractor submits for the value of work completed to date, so the consultant can review and certify it and the owner can pay it. It is the document cash moves through: every riyal that reaches the contractor passes through a certified claim first.

That is why tracking payment claims is not only an accounting task. Behind every line is a measured quantity, work that was inspected and accepted, and a rate from the bill of quantities or an approved change. When a claim is cut or paid late, the question is usually: where is the evidence for this quantity?

What types of payment are there?

Payment types in construction contracts
TypeWhenWhat it covers
Advance paymentAfter signing and providing its guarantee, if the contract allows itA share of the contract value, recovered later from interim claims
Interim payment claimPeriodically, usually monthlyValue of work done to date, less retention, advance recovery, and amounts previously certified
Final payment claimAfter taking over and settling the final accountThe final contract value after changes and settlements, and retention release by its stages

What does an interim payment claim contain?

The contract and the project template set the format, but a claim usually includes:

  • BOQ lines: contract quantity, quantity completed to date, previous, this period, unit rate, and value.
  • Materials delivered to site but not yet installed, if the contract pays a share of them.
  • Approved changes: change orders and adjustments approved in writing, not those still under negotiation.
  • Deductions: retention, advance payment recovery, and any other deduction the contract sets.
  • Amounts previously certified, so the net due for this period is clear.
  • VAT (15% in Saudi Arabia) on the net amount due.
  • Attachments: measurement sheets, accepted work inspection requests (WIRs), material inspection requests (MIRs), and the progress report.

How is a payment claim calculated? A worked example

The common method is cumulative: calculate the total value to date, subtract the deductions, then subtract what earlier claims certified. The figures below are illustrative; the contract sets the rates and their basis.

Example interim payment claim in Saudi riyals
ItemAmount
Work completed to date4,000,000
Materials on site200,000
Approved changes to date300,000
Gross cumulative value4,500,000
Less retention at 10%(450,000)
Less advance recovery at 10%(450,000)
Net cumulative value3,600,000
Less previously certified(2,700,000)
Net this claim before VAT900,000
VAT at 15%135,000
Amount due on this claim1,035,000

Contracts differ in the details. Some apply retention to work but not materials. Some cap retention at a share of the contract price and stop deducting once the cap is reached. Some start advance recovery only after progress reaches a set percentage. Materials on site are usually deducted once installed and counted in the work value, so they are not paid twice.

The claim cycle from measurement to receipt

  1. The contractor’s quantity surveyor measures completed work, based on accepted inspection requests and joint measurements with the consultant.
  2. The claim is prepared, reviewed by the contractor’s project manager, and formally submitted with its attachments.
  3. The consultant’s quantity surveyor reviews each line (quantity, rate, and evidence) and adjusts anything the evidence does not support, with a reason.
  4. The consultant’s project manager certifies the amount or returns the claim to the contractor for correction.
  5. The owner or their representative issues the interim payment certificate (IPC) for the certified amount.
  6. The contractor issues a tax invoice, and payment is recorded when received, in full or in parts.

The contract sets the deadlines. Under FIDIC (the Red Book, 1999 and 2017 editions), the Engineer issues the interim payment certificate within 28 days of receiving the contractor’s statement, and the Employer pays within 56 days of the Engineer receiving the statement, unless the particular conditions change this. A slow review is not only an administrative problem; it can breach a contractual time limit.

Retention: when it is deducted and when it is released

Retention is a percentage deducted from each interim claim, often between 5% and 10%, as security for completing the work and fixing defects. The contract sets the rate, the cap, and the release stages. Under FIDIC, half is usually released at the taking-over certificate and the other half after the defects notification period. Some contracts allow a bank guarantee in place of retention.

A common mistake is to track retention in a spreadsheet separate from the claims. At taking over it then becomes hard to prove the total withheld and when each release fell due. Retention is a cumulative balance and should appear on every claim.

Common mistakes in payment claims

  • Claiming quantities that have not been inspected or accepted, so the claim is cut and the whole payment is delayed.
  • Including change orders still under negotiation as if they were approved.
  • Editing the claim in Excel after submission without a new revision, so no one knows which version was reviewed.
  • Mixing up previous and current quantities, so a quantity is paid twice or drops out.
  • Consultant reductions without a written reason, so a later dispute has no record to refer to.
  • Tracking payments by email and phone, so no one knows the balance left on each certificate.

What should progress payment software do?

Start with one question: who uses it? If the goal is the contractor’s internal accounts (costs, invoicing, and procurement), a construction ERP is the right place. If the goal is for the contractor to submit, the consultant to review, and the owner to certify in one record everyone sees, you need:

  • Lines tied to the contract BOQ, not a spreadsheet rebuilt every month.
  • Each claimed quantity linked to its evidence: accepted work and material inspection requests.
  • Only approved changes included, linked to the decision that approved them.
  • Retention, advance recovery, and VAT calculated from the contract terms, with cumulative balances.
  • Consultant assessment of each line, with a written reason for any difference from the claimed amount.
  • Clear roles: who prepares, submits, assesses, certifies, and issues the certificate.
  • The claim locked after submission, and a history that cannot be edited for every certification, return, and payment.
  • Partial payments recorded, with certified, paid, and outstanding amounts visible for each contract.

How Mutamad handles payment claims

In Mutamad a payment claim is called a payment application and is managed from the contract’s progress and payment certification screen. The screen opens once the contract, its BOQ, the mapping of work to BOQ lines, and the payment terms are in place. The payment terms include the retention rate, cap, and release stages, the advance recovery rate, and tax.

  • The application is proposed from accepted inspection results in the Quality Center, priced against the BOQ. Materials accepted through material inspection requests enter as materials on site at the share the contract sets. Approved changes enter as separate lines.
  • The contractor’s quantity surveyor prepares the application and the contractor’s project manager submits it. The consultant’s quantity surveyor assesses each line, the consultant’s project manager certifies, and the client representative issues the interim payment certificate.
  • Any difference between the assessed and claimed amount needs a written reason, and going beyond what the evidence supports needs an exception reason.
  • Each application calculates current work, materials, and changes, retention, advance recovery, tax, the amount due, and previous and cumulative certified amounts.
  • The client representative records payments against the certificate, in full or in part, with a proof document and a bank reference, never above the outstanding balance. The Financials page shows certified, due, paid, and outstanding amounts for each contract.
  • The application and its lines cannot be edited after submission, and the history of certifications, certificates, and payments is append-only. Every formal action requires the user to confirm their identity again.
  • After certification, a bilingual PDF can be downloaded with the claimed and assessed lines and the payment certificate, plus a digital fingerprint of the certification and the certificate.

What Mutamad does not do today: it does not issue tax invoices, track the age of unpaid certificates, or forecast cash flow. Retention release at taking over and at the end of the defects period is settled in the final account, not in an interim application.

Mutamad is pre-launch, and we are now selecting three founding projects. The system never certifies an amount or issues a certificate on anyone’s behalf; certification is the decision of the authorized person on the project.

Frequently asked questions

What is the difference between a payment claim and a payment certificate?

A payment claim is what the contractor asks for, based on the work completed. An interim payment certificate is issued by the engineer or owner for the amount found due after review, which can be less than the claim. Payment follows the certificate, not the claim.

What is the difference between an interim and a final payment claim?

An interim claim is a periodic payment for work completed to date, with retention and advance recovery deducted. A final claim comes after taking over and the final account settlement, and sets the final contract value and the release of retention by its stages.

Can the consultant reduce quantities in a payment claim?

Yes, when the evidence does not support the quantity or the work has not been accepted yet. The reduction should be made line by line with a written reason, so the contractor knows what to correct or prove in the next claim and the record holds up in a dispute.

Is a certified payment claim a tax invoice?

No. The certified claim and the payment certificate establish the amount due. The contractor issues the tax invoice from their approved e-invoicing system under ZATCA rules. Link the invoice number to the claim.

When is retention released?

According to the stages in the contract. Under FIDIC, half is usually released at the taking-over certificate and the other half after the defects notification period. Some contracts allow a bank guarantee instead of retention. Your contract’s particular conditions are the reference.

The payment claim is the last link in a chain that starts with the work inspection request and the material inspection request, and passes through change orders. Read about the contractor, consultant, and owner approval chain, or apply with your project to review the payment claim cycle on your project.